|
|
|
|
|
|
|
|
||||||||||||||||||||||
|
Calculation
of Approximate Cost and Subsidy Per Passenger |
|
|
|
|
|
Estimated
|
||||||||||||||||||||||
|
Calendar
Year 2012 |
|
|
|
|
|
of
Non-Specified Initial Capital Costs and Percentages of |
||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Existing
Transit Passengers in Projected Total Ridership |
||||||||||||||
|
The calculations below
estimate the cost and subsidy per passenger on the proposed "Central |
|
|
|
|
|
Calendar
Year 2012 |
||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||||||
|
Federal Transit
Administration (FTA) for applications for 49 |
|
|
|
|
|
Percentage |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||
|
which is the program
that it appears is being assumed to provide most, if not all, of the |
|
|
|
|
|
of Existing |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||
|
assumed 50% Federal share of
the initial (identified) capital costs. |
|
|
|
|
|
|
|
|
Transit |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Passengers |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Except where otherwise
noted, the source of data utilized in this calculation is, "Central |
|
|
|
|
|
in Projected |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
||||||||
|
|
(Download from |
|
|
|
|
|
|
|
Total |
|
Non-Specified Initital Capital Costs (Millions) |
|||||||||||||||||
|
http://www.metroplanorlando.com/site/downloads/default.asp |
as "commuter rail
update.") |
|
|
|
|
|
Ridership |
|
$0 |
|
$100 |
|
$200 |
|
$300 |
|
$400 |
|
$600 |
|
$700 |
|||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
The calculation will
be done two ways, the first strictly using the costs identified in the above |
|
|
|
|
|
0% |
|
$33.32 |
|
$36.36 |
|
$39.40 |
|
$42.43 |
|
$45.47 |
|
$51.54 |
|
$54.58 |
||||||||
|
document. However, the plan, as presented, shows no
costs for rail vehicles, evidently under |
|
|
|
|
|
10% |
|
$37.03 |
|
$40.40 |
|
$43.77 |
|
$47.15 |
|
$50.52 |
|
$57.27 |
|
$60.65 |
||||||||
|
the assumption that
these will be provided by the Federal government at no cost to the local |
|
|
|
|
|
20% |
|
$41.65 |
|
$45.45 |
|
$49.25 |
|
$53.04 |
|
$56.84 |
|
$64.43 |
|
$68.23 |
||||||||
|
agencies. Assuming that this does occur, it is still
important to determine the cost of the |
|
|
|
|
|
30% |
|
$47.61 |
|
$51.94 |
|
$56.28 |
|
$60.62 |
|
$64.96 |
|
$73.64 |
|
$77.97 |
||||||||
|
project INCLUDING the cost of
rail vehicles, for reasons explained in the narrative report. |
|
|
|
|
|
40% |
|
$55.54 |
|
$60.60 |
|
$65.66 |
|
$70.72 |
|
$75.78 |
|
$85.91 |
|
$90.97 |
||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
50% |
|
$66.65 |
|
$72.72 |
|
$78.79 |
|
$84.87 |
|
$90.94 |
|
$103.09 |
|
$109.16 |
|
The projections are
for calendar year 2012, the first year when the full proposed line is |
|
|||||||||||||||||||||||||||